RPC - Enviromental
Paving the way Forward

Contact Us:
T. 01823 274232
F. 01823 274231
E. enviro@rpcltd.co.uk

LATEST NEWS: RECENT FLOODING PROMPTS INTEREST IN RPC DEFENCE SYSTEMS…
Home Email to a Friend

Ankalok - Installation


The areas to be protected should be graded to the required line and level and free from obstructions. Where a geotextile filter has been specified this should be laid onto prepared sub-grade with overlaps of not less than 300mm – multiple thicknesses should be avoided.

Following the provision of suitable toe support the Ankalok blocks are then laid in courses to a straight line working away from the toe beam. The first two courses should be laid simultaneously to ensure that the correct spacing and interlock is achieved. It should be noted that the blocks are not intended to butt tight at the ends but to have an open joint of approximately 10mm.

Following installation of the first two courses it is advisable to set string lines perpendicular to the toe at approximately 6m centres thus maintaining a constant course length and ensuring that the revetment remains square and uniform.

Filling and Seeding
On completion of installation the open cells and joints of the revetments should be filled with material relative to the nature of the applications. Below normal water level this may take the form of angular gravel, suggested grading of which is 10-15mm. Above water level the cells may be filled with selected top soil and sown with a seed mixture suitable to the location.
(Ref: CIRIA R116)

Additional Anchoring
Additional anchorage of revetment may be provided by the installation of 40mm square timber of 25mm diameter mild steel pegs driven through selected block cells. Where it is difficult to provide a satisfactory toe support at the base of the revetment additional restraint can be provided along the top of the revetment by installing timber or steel pegs at one per block i.e. 0.4m centres.



Concrete Solutions
Contracts
Paving Solutions