Dycel
- Installation |
|
| Hand laid
The area to be protected should be prepared as for articulated
panels, though a suitable toe support will be necessary.
The Dycel blocks are then laid to a stretcher
bond working away from the toe beam. The first two courses
should be laid simultaneously to ensure that the correct spacing
and interlock is achieved.
Following installation of the first two
courses it is advisable to set string lines perpendicular
to the toe at approximately 6m centres, thus maintaining a
constant course length and ensuring the panel remains square.
Filling
and seeding
On completion of installation the open cells and joints of
the revetment may be filled with material relative to the
nature of the application.
Below normal water level this fill may take
the form of angular gravel and above this level the cells
may be filled with a selected top soil and sown with a seed
mixture suitable to the location.
(Ref. CIRIA R116)
|
|
|
|
|
| |